The books should soon be closed on the Butler County Government Center Annex project.
The commissioners approved more than $60,000 worth of change orders this week for things like adding a power supply to a door and modifying some hallway ceilings. County Director of Operations John Campbell said the changes were things that were missed earlier but had to be done per code.
Commissioner Leslie Osche said the $12 million project is still under budget. It houses the county’s human services department and is accessible through the Government Center.